Original Cost
₹1081 Cr
Baseline estimate
Revised Cost
₹1081 Cr
Latest approved cost
Expenditure
₹958 Cr
Spent to date
Utilization
88.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹122 Cr
Budget left
Spent
₹958 Cr
Remaining
₹122 Cr
Total
₹1081 Cr
Project Approved
Construction / Implementation
Original End Date
31/10/2026
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹1081 Cr — no cost escalation recorded.
Expenditure stands at ₹958 Cr, which is 88.7% of the revised project cost.
Remaining budget: ₹122 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.