Original Cost
₹189 Cr
Baseline estimate
Revised Cost
₹189 Cr
Latest approved cost
Expenditure
₹56 Cr
Spent to date
Utilization
29.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹133 Cr
Budget left
Spent
₹56 Cr
Remaining
₹133 Cr
Total
₹189 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2028
Revised Completion
Completed
Project is within original budget of ₹189 Cr — no cost escalation recorded.
Expenditure stands at ₹56 Cr, which is 29.4% of the revised project cost.
Remaining budget: ₹133 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.