New BG line
Original Cost
₹2555 Cr
Baseline estimate
Revised Cost
₹2555 Cr
Latest approved cost
Expenditure
₹1114 Cr
Spent to date
Utilization
43.6%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹1441 Cr
Budget left
Spent
₹1114 Cr
Remaining
₹1441 Cr
Total
₹2555 Cr
43.6%
Utilized
Project Approved
Construction / Implementation
Original End Date
2028-03-31
Revised Completion
2028-03-31
Completed
Project is within original budget of ₹2555 Cr — no cost escalation recorded.
Expenditure stands at ₹1114 Cr, which is 43.6% of the revised project cost.
Remaining budget: ₹1441 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.