Original Cost
₹2786 Cr
Baseline estimate
Revised Cost
₹2786 Cr
Latest approved cost
Expenditure
₹260 Cr
Spent to date
Utilization
9.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹2526 Cr
Budget left
Spent
₹260 Cr
Remaining
₹2526 Cr
Total
₹2786 Cr
Project Approved
Construction / Implementation
Original End Date
30/10/2028
Revised Completion
Completed
Project is within original budget of ₹2786 Cr — no cost escalation recorded.
Expenditure stands at ₹260 Cr, which is 9.3% of the revised project cost.
Remaining budget: ₹2526 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Real Estate. Ministry: Department for Promotion of Industry & Internal Trade.