Original Cost
₹495 Cr
Baseline estimate
Revised Cost
₹825 Cr
Latest approved cost
Expenditure
₹285 Cr
Spent to date
Utilization
34.5%
Of revised budget
Cost Status
+66.7%
+₹330 Cr increase
Remaining
₹540 Cr
Budget left
Spent
₹285 Cr
Remaining
₹540 Cr
Total
₹825 Cr
Original Cost
₹495 Cr
Revised Cost
₹825 Cr
Increase
+₹330 Cr
Escalation
+66.7%
Project Approved
Construction / Implementation
Original End Date
31/03/2026
Revised Completion
30/06/2026
Completed
Cost has increased by ₹330 Cr (66.7%) from the original estimate of ₹495 Cr.
Expenditure stands at ₹285 Cr, which is 34.5% of the revised project cost.
Remaining budget: ₹540 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.