Original Cost
₹2400 Cr
Baseline estimate
Revised Cost
₹3425 Cr
Latest approved cost
Expenditure
₹2713 Cr
Spent to date
Utilization
79.2%
Of revised budget
Cost Status
+42.7%
+₹1025 Cr increase
Remaining
₹712 Cr
Budget left
Spent
₹2713 Cr
Remaining
₹712 Cr
Total
₹3425 Cr
Original Cost
₹2400 Cr
Revised Cost
₹3425 Cr
Increase
+₹1025 Cr
Escalation
+42.7%
Project Approved
Construction / Implementation
Original End Date
31/12/2025
Revised Completion
31/01/2027
Completed
Cost has increased by ₹1025 Cr (42.7%) from the original estimate of ₹2400 Cr.
Expenditure stands at ₹2713 Cr, which is 79.2% of the revised project cost.
Remaining budget: ₹712 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.