Original Cost
₹2312 Cr
Baseline estimate
Revised Cost
₹5932 Cr
Latest approved cost
Expenditure
₹3119 Cr
Spent to date
Utilization
52.6%
Of revised budget
Cost Status
+156.6%
+₹3620 Cr increase
Remaining
₹2813 Cr
Budget left
Spent
₹3119 Cr
Remaining
₹2813 Cr
Total
₹5932 Cr
Original Cost
₹2312 Cr
Revised Cost
₹5932 Cr
Increase
+₹3620 Cr
Escalation
+156.6%
Project Approved
Construction / Implementation
Original End Date
31/05/2027
Revised Completion
31/03/2028
Completed
Cost has increased by ₹3620 Cr (156.6%) from the original estimate of ₹2312 Cr.
Expenditure stands at ₹3119 Cr, which is 52.6% of the revised project cost.
Remaining budget: ₹2813 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.