Original Cost
₹435 Cr
Baseline estimate
Revised Cost
₹1250 Cr
Latest approved cost
Expenditure
₹868 Cr
Spent to date
Utilization
69.4%
Of revised budget
Cost Status
+187.4%
+₹815 Cr increase
Remaining
₹382 Cr
Budget left
Spent
₹868 Cr
Remaining
₹382 Cr
Total
₹1250 Cr
Original Cost
₹435 Cr
Revised Cost
₹1250 Cr
Increase
+₹815 Cr
Escalation
+187.4%
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
31/12/2026
Completed
Cost has increased by ₹815 Cr (187.4%) from the original estimate of ₹435 Cr.
Expenditure stands at ₹868 Cr, which is 69.4% of the revised project cost.
Remaining budget: ₹382 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.