Original Cost
₹484 Cr
Baseline estimate
Revised Cost
₹1039 Cr
Latest approved cost
Expenditure
₹724 Cr
Spent to date
Utilization
69.6%
Of revised budget
Cost Status
+114.7%
+₹555 Cr increase
Remaining
₹316 Cr
Budget left
Spent
₹724 Cr
Remaining
₹316 Cr
Total
₹1039 Cr
Original Cost
₹484 Cr
Revised Cost
₹1039 Cr
Increase
+₹555 Cr
Escalation
+114.7%
Project Approved
Construction / Implementation
Original End Date
31/03/2021
Revised Completion
31/12/2026
Completed
Cost has increased by ₹555 Cr (114.7%) from the original estimate of ₹484 Cr.
Expenditure stands at ₹724 Cr, which is 69.6% of the revised project cost.
Remaining budget: ₹316 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.