Waste & WaterIPM · Central Project#702840

Mira-Bhayandar Water Supply Infrastructure Project

Ministry of Housing & Urban AffairsMaharashtra
Revised Cost: ₹205 CrUtilization: 90.8%

Original Cost

₹205 Cr

Baseline estimate

On budget

Revised Cost

₹205 Cr

Latest approved cost

Expenditure

₹186 Cr

Spent to date

Utilization

90.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹19 Cr

Budget left

Budget Utilization

90.8%
0%25%50%75%100%

Spent

₹186 Cr

Remaining

₹19 Cr

Total

₹205 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2023

Revised Completion

31/05/2026

Completed

Project Details

Project Code702840
SectorWaste & Water
MinistryMinistry of Housing & Urban Affairs
StateMaharashtra
Data Month2026-04

Financial Summary

Original Cost₹205 Cr
Revised Cost₹205 Cr
Expenditure₹186 Cr
Original End Date31/03/2023
Revised Date31/05/2026

Project Intelligence

Project is within original budget of ₹205 Cr — no cost escalation recorded.

Expenditure stands at ₹186 Cr, which is 90.8% of the revised project cost.

Remaining budget: ₹19 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Waste & Water. Ministry: Ministry of Housing & Urban Affairs.

Mira-Bhayandar Water Supply Infrastructure Project is a centrally-funded infrastructure project under Ministry of Housing & Urban Affairs, in the Waste & Water sector. The original approved cost is ₹205.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Mira-Bhayandar Water Supply Infrastructure Project"?
Mira-Bhayandar Water Supply Infrastructure Project is a centrally-funded infrastructure project under the Ministry of Housing & Urban Affairs, tracked through the Investment Project Monitoring (IPM) system. Sector: Waste & Water. State: Maharashtra. Original cost: ₹205 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹205 Cr has not been significantly revised. Expenditure: ₹186 Cr (90.8% of cost). Data as of 2026-04.
QWhich ministry is responsible for this project?
Mira-Bhayandar Water Supply Infrastructure Project is under the Ministry of Housing & Urban Affairs in the Waste & Water sector. Project code: 702840. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Mira-Bhayandar Water Supply Infrastructure Project is one of several Bihar projects tracked under the Waste & Water sector on the IPM system.