Original Cost
₹205 Cr
Baseline estimate
Revised Cost
₹205 Cr
Latest approved cost
Expenditure
₹186 Cr
Spent to date
Utilization
90.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹19 Cr
Budget left
Spent
₹186 Cr
Remaining
₹19 Cr
Total
₹205 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2023
Revised Completion
31/05/2026
Completed
Project is within original budget of ₹205 Cr — no cost escalation recorded.
Expenditure stands at ₹186 Cr, which is 90.8% of the revised project cost.
Remaining budget: ₹19 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Waste & Water. Ministry: Ministry of Housing & Urban Affairs.