Original Cost
₹601 Cr
Baseline estimate
Revised Cost
₹2084 Cr
Latest approved cost
Expenditure
₹351 Cr
Spent to date
Utilization
16.8%
Of revised budget
Cost Status
+246.8%
+₹1483 Cr increase
Remaining
₹1733 Cr
Budget left
Spent
₹351 Cr
Remaining
₹1733 Cr
Total
₹2084 Cr
Original Cost
₹601 Cr
Revised Cost
₹2084 Cr
Increase
+₹1483 Cr
Escalation
+246.8%
Project Approved
Construction / Implementation
Original End Date
31/07/2021
Revised Completion
31/01/2031
Completed
Cost has increased by ₹1483 Cr (246.8%) from the original estimate of ₹601 Cr.
Expenditure stands at ₹351 Cr, which is 16.8% of the revised project cost.
Remaining budget: ₹1733 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.