Original Cost
₹304 Cr
Baseline estimate
Revised Cost
₹356 Cr
Latest approved cost
Expenditure
₹249 Cr
Spent to date
Utilization
69.8%
Of revised budget
Cost Status
+17.1%
+₹52 Cr increase
Remaining
₹107 Cr
Budget left
Spent
₹249 Cr
Remaining
₹107 Cr
Total
₹356 Cr
Original Cost
₹304 Cr
Revised Cost
₹356 Cr
Increase
+₹52 Cr
Escalation
+17.1%
Project Approved
Construction / Implementation
Original End Date
31/12/2024
Revised Completion
31/01/2026
Completed
Cost has increased by ₹52 Cr (17.1%) from the original estimate of ₹304 Cr.
Expenditure stands at ₹249 Cr, which is 69.8% of the revised project cost.
Remaining budget: ₹107 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.