Original Cost
₹468 Cr
Baseline estimate
Revised Cost
₹468 Cr
Latest approved cost
Expenditure
₹45 Cr
Spent to date
Utilization
9.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹423 Cr
Budget left
Spent
₹45 Cr
Remaining
₹423 Cr
Total
₹468 Cr
Project Approved
Construction / Implementation
Original End Date
30/03/2027
Revised Completion
Completed
Project is within original budget of ₹468 Cr — no cost escalation recorded.
Expenditure stands at ₹45 Cr, which is 9.5% of the revised project cost.
Remaining budget: ₹423 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.