Line
Original Cost
₹1626 Cr
Baseline estimate
Revised Cost
₹2487 Cr
Latest approved cost
Expenditure
₹2215 Cr
Spent to date
Utilization
89.1%
Of revised cost
Cost Overrun
+52.9%
+₹861 Cr
Remaining
₹271 Cr
Budget left
Spent
₹2215 Cr
Remaining
₹271 Cr
Total
₹2487 Cr
89.1%
Utilized
Original Cost
₹1626 Cr
Revised Cost
₹2487 Cr
Increase
+₹861 Cr
Escalation
+52.9%
Project Approved
Construction / Implementation
Original End Date
2025-02-28
Revised Completion
2026-02-28
Completed
Cost has increased by ₹861 Cr (52.9%) from the original estimate of ₹1626 Cr.
Expenditure stands at ₹2215 Cr, which is 89.1% of the revised project cost.
Remaining budget: ₹271 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.