Original Cost
₹14.3K Cr
Baseline estimate
Revised Cost
₹21.9K Cr
Latest approved cost
Expenditure
₹16.2K Cr
Spent to date
Utilization
74.1%
Of revised budget
Cost Status
+52.8%
+₹7563 Cr increase
Remaining
₹5660 Cr
Budget left
Spent
₹16.2K Cr
Remaining
₹5660 Cr
Total
₹21.9K Cr
Original Cost
₹14.3K Cr
Revised Cost
₹21.9K Cr
Increase
+₹7563 Cr
Escalation
+52.8%
Project Approved
Construction / Implementation
Original End Date
31/12/2026
Revised Completion
30/06/2029
Completed
Mega infrastructure project worth ₹21.9K Cr — among the largest central projects in Manipur.
Cost has increased by ₹7563 Cr (52.8%) from the original estimate of ₹14.3K Cr.
Expenditure stands at ₹16.2K Cr, which is 74.1% of the revised project cost.
Remaining budget: ₹5660 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.