Original Cost
₹562 Cr
Baseline estimate
Revised Cost
₹562 Cr
Latest approved cost
Expenditure
₹486 Cr
Spent to date
Utilization
86.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹76 Cr
Budget left
Spent
₹486 Cr
Remaining
₹76 Cr
Total
₹562 Cr
Project Approved
Construction / Implementation
Original End Date
31/07/2023
Revised Completion
31/05/2026
Completed
Project is within original budget of ₹562 Cr — no cost escalation recorded.
Expenditure stands at ₹486 Cr, which is 86.5% of the revised project cost.
Remaining budget: ₹76 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Waste & Water. Ministry: Ministry of Housing & Urban Affairs.