Original Cost
₹259 Cr
Baseline estimate
Revised Cost
₹267 Cr
Latest approved cost
Expenditure
₹161 Cr
Spent to date
Utilization
60.4%
Of revised budget
Cost Status
+2.9%
+₹8 Cr increase
Remaining
₹106 Cr
Budget left
Spent
₹161 Cr
Remaining
₹106 Cr
Total
₹267 Cr
Original Cost
₹259 Cr
Revised Cost
₹267 Cr
Increase
+₹8 Cr
Escalation
+2.9%
Project Approved
Construction / Implementation
Original End Date
28/08/2023
Revised Completion
31/08/2026
Completed
Cost has increased by ₹8 Cr (2.9%) from the original estimate of ₹259 Cr.
Expenditure stands at ₹161 Cr, which is 60.4% of the revised project cost.
Remaining budget: ₹106 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Waste & Water. Ministry: Ministry of Housing & Urban Affairs.