Waste & WaterIPM · Central Project +2.9% overrun#703021

Jalandhar Water Supply Infrastructure Project

Ministry of Housing & Urban AffairsPunjab
Revised Cost: ₹267 CrUtilization: 60.4%Overrun: +₹8 Cr

Original Cost

₹259 Cr

Baseline estimate

+3% overrun

Revised Cost

₹267 Cr

Latest approved cost

Expenditure

₹161 Cr

Spent to date

Utilization

60.4%

Of revised budget

Escalated

Cost Status

+2.9%

+₹8 Cr increase

Remaining

₹106 Cr

Budget left

Budget Utilization

60.4%
0%25%50%75%100%

Spent

₹161 Cr

Remaining

₹106 Cr

Total

₹267 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹259 Cr

Revised Cost

₹267 Cr

Increase

+₹8 Cr

Escalation

+2.9%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

28/08/2023

Revised Completion

31/08/2026

Completed

Project Details

Project Code703021
SectorWaste & Water
MinistryMinistry of Housing & Urban Affairs
StatePunjab
Data Month2026-08

Financial Summary

Original Cost₹259 Cr
Revised Cost₹267 Cr
Expenditure₹161 Cr
Original End Date28/08/2023
Revised Date31/08/2026

Project Intelligence

Cost has increased by ₹8 Cr (2.9%) from the original estimate of ₹259 Cr.

Expenditure stands at ₹161 Cr, which is 60.4% of the revised project cost.

Remaining budget: ₹106 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Waste & Water. Ministry: Ministry of Housing & Urban Affairs.

Jalandhar Water Supply Infrastructure Project is a centrally-funded infrastructure project under Ministry of Housing & Urban Affairs, in the Waste & Water sector. The original approved cost is ₹259.00 Cr, later revised to ₹266.64 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Jalandhar Water Supply Infrastructure Project"?
Jalandhar Water Supply Infrastructure Project is a centrally-funded infrastructure project under the Ministry of Housing & Urban Affairs, tracked through the Investment Project Monitoring (IPM) system. Sector: Waste & Water. State: Punjab. Original cost: ₹259 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹259 Cr and has been revised to ₹267 Cr — a cost overrun of +2.9%. Expenditure to date: ₹161 Cr (60.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Jalandhar Water Supply Infrastructure Project is under the Ministry of Housing & Urban Affairs in the Waste & Water sector. Project code: 703021. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Jalandhar Water Supply Infrastructure Project is one of several Bihar projects tracked under the Waste & Water sector on the IPM system.