Inland WaterwaysIPM · Central Project#701565

Jal Marg Vikas Project

Ministry of Ports, Shipping and WaterwaysWest Bengal
Revised Cost: ₹5061 CrUtilization: 82.7%

Original Cost

₹5369 Cr

Baseline estimate

On budget

Revised Cost

₹5061 Cr

Latest approved cost

Expenditure

₹4187 Cr

Spent to date

Utilization

82.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹874 Cr

Budget left

Budget Utilization

82.7%
0%25%50%75%100%

Spent

₹4187 Cr

Remaining

₹874 Cr

Total

₹5061 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2023

Revised Completion

24/10/2026

Completed

Project Details

Project Code701565
SectorInland Waterways
MinistryMinistry of Ports, Shipping and Waterways
StateWest Bengal
Data Month2026-07

Financial Summary

Original Cost₹5369 Cr
Revised Cost₹5061 Cr
Expenditure₹4187 Cr
Original End Date31/12/2023
Revised Date24/10/2026

Project Intelligence

Project is within original budget of ₹5369 Cr — no cost escalation recorded.

Expenditure stands at ₹4187 Cr, which is 82.7% of the revised project cost.

Remaining budget: ₹874 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Inland Waterways. Ministry: Ministry of Ports, Shipping and Waterways.

Jal Marg Vikas Project is a centrally-funded infrastructure project under Ministry of Ports, Shipping and Waterways, in the Inland Waterways sector. The original approved cost is ₹5369.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Jal Marg Vikas Project"?
Jal Marg Vikas Project is a centrally-funded infrastructure project under the Ministry of Ports, Shipping and Waterways, tracked through the Investment Project Monitoring (IPM) system. Sector: Inland Waterways. State: West Bengal. Original cost: ₹5369 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹5369 Cr and has been revised to ₹5061 Cr — a cost overrun of -5.7%. Expenditure to date: ₹4187 Cr (82.7% of revised cost). Data as of 2026-07.
QWhich ministry is responsible for this project?
Jal Marg Vikas Project is under the Ministry of Ports, Shipping and Waterways in the Inland Waterways sector. Project code: 701565. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Jal Marg Vikas Project is one of several Bihar projects tracked under the Inland Waterways sector on the IPM system.