Waste & WaterIPM · Central Project#616594

Interception & Diversion with Rehabilitation of sewerage scheme at Agra under Hybrid annuity based PPP model-Namami Gange Programme

Department of Water Resources, River Development & GRUttar Pradesh
Revised Cost: ₹842 CrUtilization: 24.8%

Original Cost

₹842 Cr

Baseline estimate

On budget

Revised Cost

₹842 Cr

Latest approved cost

Expenditure

₹209 Cr

Spent to date

Utilization

24.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹633 Cr

Budget left

Budget Utilization

24.8%
0%25%50%75%100%

Spent

₹209 Cr

Remaining

₹633 Cr

Total

₹842 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/04/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code616594
SectorWaste & Water
MinistryDepartment of Water Resources, River Development & GR
StateUttar Pradesh
Data Month2026-08

Financial Summary

Original Cost₹842 Cr
Revised Cost₹842 Cr
Expenditure₹209 Cr
Original End Date30/04/2025
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹842 Cr — no cost escalation recorded.

Expenditure stands at ₹209 Cr, which is 24.8% of the revised project cost.

Remaining budget: ₹633 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Waste & Water. Ministry: Department of Water Resources, River Development & GR.

Interception & Diversion with Rehabilitation of sewerage scheme at Agra under Hybrid annuity based PPP model-Namami Gange Programme is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Waste & Water sector. The original approved cost is ₹842.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Interception & Diversion with Rehabilitation of sewerage scheme at Agra under Hy"?
Interception & Diversion with Rehabilitation of sewerage scheme at Agra under Hybrid annuity based PPP model-Namami Gange Programme is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Waste & Water. State: Uttar Pradesh. Original cost: ₹842 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹842 Cr has not been significantly revised. Expenditure: ₹209 Cr (24.8% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Interception & Diversion with Rehabilitation of sewerage sch is under the Department of Water Resources, River Development & GR in the Waste & Water sector. Project code: 616594. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Interception & Diversion with Rehabilitation of sewerage sch is one of several Bihar projects tracked under the Waste & Water sector on the IPM system.