Hybrid annuity based PPP mode-Namami Gange Programme
Original Cost
₹413 Cr
Baseline estimate
Revised Cost
₹413 Cr
Latest approved cost
Expenditure
₹127 Cr
Spent to date
Utilization
30.7%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹286 Cr
Budget left
Spent
₹127 Cr
Remaining
₹286 Cr
Total
₹413 Cr
30.7%
Utilized
Project Approved
Construction / Implementation
Original End Date
2025-02-06
Revised Completion
2026-12-31
Completed
Project is within original budget of ₹413 Cr — no cost escalation recorded.
Expenditure stands at ₹127 Cr, which is 30.7% of the revised project cost.
Remaining budget: ₹286 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Waste & Water. Ministry: Department of Water Resources, River Development & GR.