Real EstateIPM · Central Project +9.5% overrun#707229

Integrated Command control Center [ICCC] - Construction and Development of Integrated Command Control Center with Security, Surveillance, ITMS, Connecting Port, Ship Service, Smart Solid Waste Management, Smart Public Transport System

Ministry of Housing & Urban AffairsAndaman & Nicobar
Revised Cost: ₹230 CrUtilization: 16.2%Overrun: +₹20 Cr

Original Cost

₹210 Cr

Baseline estimate

+10% overrun

Revised Cost

₹230 Cr

Latest approved cost

Expenditure

₹37 Cr

Spent to date

Utilization

16.2%

Of revised budget

Escalated

Cost Status

+9.5%

+₹20 Cr increase

Remaining

₹193 Cr

Budget left

Budget Utilization

16.2%
0%25%50%75%100%

Spent

₹37 Cr

Remaining

₹193 Cr

Total

₹230 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹210 Cr

Revised Cost

₹230 Cr

Increase

+₹20 Cr

Escalation

+9.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/05/2023

Revised Completion

31/10/2025

Completed

Project Details

Project Code707229
SectorReal Estate
MinistryMinistry of Housing & Urban Affairs
StateAndaman & Nicobar
Data Month2026-08

Financial Summary

Original Cost₹210 Cr
Revised Cost₹230 Cr
Expenditure₹37 Cr
Original End Date31/05/2023
Revised Date31/10/2025

Project Intelligence

Cost has increased by ₹20 Cr (9.5%) from the original estimate of ₹210 Cr.

Expenditure stands at ₹37 Cr, which is 16.2% of the revised project cost.

Remaining budget: ₹193 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Real Estate. Ministry: Ministry of Housing & Urban Affairs.

Integrated Command control Center [ICCC] - Construction and Development of Integrated Command Control Center with Security, Surveillance, ITMS, Connecting Port, Ship Service, Smart Solid Waste Management, Smart Public Transport System is a centrally-funded infrastructure project under Ministry of Housing & Urban Affairs, in the Real Estate sector. The original approved cost is ₹210.00 Cr, later revised to ₹230.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Integrated Command control Center [ICCC] - Construction and Development of Integ"?
Integrated Command control Center [ICCC] - Construction and Development of Integrated Command Control Center with Security, Surveillance, ITMS, Connecting Port, Ship Service, Smart Solid Waste Management, Smart Public Transport System is a centrally-funded infrastructure project under the Ministry of Housing & Urban Affairs, tracked through the Investment Project Monitoring (IPM) system. Sector: Real Estate. State: Andaman & Nicobar. Original cost: ₹210 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹210 Cr and has been revised to ₹230 Cr — a cost overrun of +9.5%. Expenditure to date: ₹37 Cr (16.2% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Integrated Command control Center [ICCC] - Construction and is under the Ministry of Housing & Urban Affairs in the Real Estate sector. Project code: 707229. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Integrated Command control Center [ICCC] - Construction and is one of several Bihar projects tracked under the Real Estate sector on the IPM system.