Integrated Command control Center [ICCC] - Construction and Development of Integrated Command Control Center with Security, Surveillance, ITMS, Connecting Port, Ship Service, Smart Solid Waste Management, Smart Public Transport System
Original Cost
₹210 Cr
Baseline estimate
Revised Cost
₹230 Cr
Latest approved cost
Expenditure
₹37 Cr
Spent to date
Utilization
16.2%
Of revised budget
Cost Status
+9.5%
+₹20 Cr increase
Remaining
₹193 Cr
Budget left
Budget Utilization
16.2%Spent
₹37 Cr
Remaining
₹193 Cr
Total
₹230 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹210 Cr
Revised Cost
₹230 Cr
Increase
+₹20 Cr
Escalation
+9.5%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/05/2023
Revised Completion
31/10/2025
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹20 Cr (9.5%) from the original estimate of ₹210 Cr.
Expenditure stands at ₹37 Cr, which is 16.2% of the revised project cost.
Remaining budget: ₹193 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Real Estate. Ministry: Ministry of Housing & Urban Affairs.
Integrated Command control Center [ICCC] - Construction and Development of Integrated Command Control Center with Security, Surveillance, ITMS, Connecting Port, Ship Service, Smart Solid Waste Management, Smart Public Transport System is a centrally-funded infrastructure project under Ministry of Housing & Urban Affairs, in the Real Estate sector. The original approved cost is ₹210.00 Cr, later revised to ₹230.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Integrated Command control Center [ICCC] - Construction and Development of Integ"?
- Integrated Command control Center [ICCC] - Construction and Development of Integrated Command Control Center with Security, Surveillance, ITMS, Connecting Port, Ship Service, Smart Solid Waste Management, Smart Public Transport System is a centrally-funded infrastructure project under the Ministry of Housing & Urban Affairs, tracked through the Investment Project Monitoring (IPM) system. Sector: Real Estate. State: Andaman & Nicobar. Original cost: ₹210 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹210 Cr and has been revised to ₹230 Cr — a cost overrun of +9.5%. Expenditure to date: ₹37 Cr (16.2% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Integrated Command control Center [ICCC] - Construction and is under the Ministry of Housing & Urban Affairs in the Real Estate sector. Project code: 707229. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Integrated Command control Center [ICCC] - Construction and is one of several Bihar projects tracked under the Real Estate sector on the IPM system.