Original Cost
₹287 Cr
Baseline estimate
Revised Cost
₹287 Cr
Latest approved cost
Expenditure
₹253 Cr
Spent to date
Utilization
88.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹35 Cr
Budget left
Spent
₹253 Cr
Remaining
₹35 Cr
Total
₹287 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2023
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹287 Cr — no cost escalation recorded.
Expenditure stands at ₹253 Cr, which is 88.0% of the revised project cost.
Remaining budget: ₹35 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Waste & Water. Ministry: Ministry of Housing & Urban Affairs.