Original Cost
₹455 Cr
Baseline estimate
Revised Cost
₹455 Cr
Latest approved cost
Expenditure
₹205 Cr
Spent to date
Utilization
45.0%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹250 Cr
Budget left
Spent
₹205 Cr
Remaining
₹250 Cr
Total
₹455 Cr
45.0%
Utilized
Project Approved
Construction / Implementation
Original End Date
2024-03-31
Revised Completion
Completed
Project is within original budget of ₹455 Cr — no cost escalation recorded.
Expenditure stands at ₹205 Cr, which is 45.0% of the revised project cost.
Remaining budget: ₹250 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Real Estate. Ministry: Ministry of Housing & Urban Affairs.