line
Original Cost
₹2067 Cr
Baseline estimate
Revised Cost
₹2087 Cr
Latest approved cost
Expenditure
₹2084 Cr
Spent to date
Utilization
99.9%
Of revised cost
Cost Overrun
+1.0%
+₹20 Cr
Remaining
₹3 Cr
Budget left
Spent
₹2084 Cr
Remaining
₹3 Cr
Total
₹2087 Cr
99.9%
Utilized
Original Cost
₹2067 Cr
Revised Cost
₹2087 Cr
Increase
+₹20 Cr
Escalation
+1.0%
Project Approved
Construction / Implementation
Original End Date
2020-03-31
Revised Completion
2027-06-30
Completed
Cost has increased by ₹20 Cr (1.0%) from the original estimate of ₹2067 Cr.
Expenditure stands at ₹2084 Cr, which is 99.9% of the revised project cost.
Remaining budget: ₹3 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.