Original Cost
₹819 Cr
Baseline estimate
Revised Cost
₹967 Cr
Latest approved cost
Expenditure
₹405 Cr
Spent to date
Utilization
41.9%
Of revised budget
Cost Status
+18.1%
+₹148 Cr increase
Remaining
₹562 Cr
Budget left
Spent
₹405 Cr
Remaining
₹562 Cr
Total
₹967 Cr
Original Cost
₹819 Cr
Revised Cost
₹967 Cr
Increase
+₹148 Cr
Escalation
+18.1%
Project Approved
Construction / Implementation
Original End Date
30/11/2026
Revised Completion
30/11/2026
Completed
Cost has increased by ₹148 Cr (18.1%) from the original estimate of ₹819 Cr.
Expenditure stands at ₹405 Cr, which is 41.9% of the revised project cost.
Remaining budget: ₹562 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.