Original Cost
₹151 Cr
Baseline estimate
Revised Cost
₹206 Cr
Latest approved cost
Expenditure
₹57 Cr
Spent to date
Utilization
27.6%
Of revised budget
Cost Status
+36.4%
+₹55 Cr increase
Remaining
₹149 Cr
Budget left
Spent
₹57 Cr
Remaining
₹149 Cr
Total
₹206 Cr
Original Cost
₹151 Cr
Revised Cost
₹206 Cr
Increase
+₹55 Cr
Escalation
+36.4%
Project Approved
Construction / Implementation
Original End Date
23/11/2023
Revised Completion
31/12/2026
Completed
Cost has increased by ₹55 Cr (36.4%) from the original estimate of ₹151 Cr.
Expenditure stands at ₹57 Cr, which is 27.6% of the revised project cost.
Remaining budget: ₹149 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Real Estate. Ministry: Ministry of Housing & Urban Affairs.
IPM Central Project Dashboard
All central infrastructure projects in Bihar
ProjectsBihar State Projects
State-funded infrastructure project tracker
NHAINHAI Drone Tracker
Real-time NHAI highway construction monitoring
RailwayBihar Railway Projects
Railway infrastructure project tracker
RCDBihar RCD PMIS
State road and bridge project tracker
TendersBihar Government Tenders
Procurement notices for infrastructure projects
CabinetBihar Cabinet Decisions
Policy approvals for infrastructure
ECEC & Forest Clearances
Environmental clearances for Bihar projects
UpcomingUpcoming Bihar Projects
Infrastructure pipeline and future projects
DistrictsBihar District Data
District demographics and infrastructure overview