to Biharsharif, Biharsharif to Barbigha , Barbigha to Shekhpura
Original Cost
₹1473 Cr
Baseline estimate
Revised Cost
₹2882 Cr
Latest approved cost
Expenditure
₹2641 Cr
Spent to date
Utilization
91.6%
Of revised cost
Cost Overrun
+95.7%
+₹1409 Cr
Remaining
₹241 Cr
Budget left
Spent
₹2641 Cr
Remaining
₹241 Cr
Total
₹2882 Cr
91.6%
Utilized
Original Cost
₹1473 Cr
Revised Cost
₹2882 Cr
Increase
+₹1409 Cr
Escalation
+95.7%
Project Approved
Construction / Implementation
Original End Date
2023-03-31
Revised Completion
2025-08-31
Completed
Cost has increased by ₹1409 Cr (95.7%) from the original estimate of ₹1473 Cr.
Expenditure stands at ₹2641 Cr, which is 91.6% of the revised project cost.
Remaining budget: ₹241 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.