Revised Cost: ₹325 CrUtilization: 53.2%

Original Cost

₹325 Cr

Baseline estimate

On budget

Revised Cost

₹325 Cr

Latest approved cost

Expenditure

₹173 Cr

Spent to date

Utilization

53.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹152 Cr

Budget left

Budget Utilization

53.2%
0%25%50%75%100%

Spent

₹173 Cr

Remaining

₹152 Cr

Total

₹325 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

01/01/1900

Revised Completion

Completed

Project Details

Project Code707052
SectorHealthcare
MinistryMinistry of Health & Family Welfare
StateJammu & Kashmir
Data Month2026-07

Financial Summary

Original Cost₹325 Cr
Revised Cost₹325 Cr
Expenditure₹173 Cr
Original End Date01/01/1900
Revised DateN/A

Project Intelligence

Project is within original budget of ₹325 Cr — no cost escalation recorded.

Expenditure stands at ₹173 Cr, which is 53.2% of the revised project cost.

Remaining budget: ₹152 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Healthcare. Ministry: Ministry of Health & Family Welfare.

Establishment of new GMC Handwara [Distt. Kupwara] is a centrally-funded infrastructure project under Ministry of Health & Family Welfare, in the Healthcare sector. The original approved cost is ₹325.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Establishment of new GMC Handwara [Distt. Kupwara]"?
Establishment of new GMC Handwara [Distt. Kupwara] is a centrally-funded infrastructure project under the Ministry of Health & Family Welfare, tracked through the Investment Project Monitoring (IPM) system. Sector: Healthcare. State: Jammu & Kashmir. Original cost: ₹325 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹325 Cr has not been significantly revised. Expenditure: ₹173 Cr (53.2% of cost). Data as of 2026-07.
QWhich ministry is responsible for this project?
Establishment of new GMC Handwara [Distt. Kupwara] is under the Ministry of Health & Family Welfare in the Healthcare sector. Project code: 707052. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Establishment of new GMC Handwara [Distt. Kupwara] is one of several Bihar projects tracked under the Healthcare sector on the IPM system.