Original Cost
₹2500 Cr
Baseline estimate
Revised Cost
₹2500 Cr
Latest approved cost
Expenditure
₹2218 Cr
Spent to date
Utilization
88.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹282 Cr
Budget left
Spent
₹2218 Cr
Remaining
₹282 Cr
Total
₹2500 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2022
Revised Completion
31/03/2028
Completed
Project is within original budget of ₹2500 Cr — no cost escalation recorded.
Expenditure stands at ₹2218 Cr, which is 88.7% of the revised project cost.
Remaining budget: ₹282 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.