Original Cost
₹3029 Cr
Baseline estimate
Revised Cost
₹3029 Cr
Latest approved cost
Expenditure
₹2649 Cr
Spent to date
Utilization
87.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹380 Cr
Budget left
Spent
₹2649 Cr
Remaining
₹380 Cr
Total
₹3029 Cr
Project Approved
Construction / Implementation
Original End Date
30/06/2025
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹3029 Cr — no cost escalation recorded.
Expenditure stands at ₹2649 Cr, which is 87.5% of the revised project cost.
Remaining budget: ₹380 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.