Original Cost
₹338 Cr
Baseline estimate
Revised Cost
₹205 Cr
Latest approved cost
Expenditure
₹29 Cr
Spent to date
Utilization
14.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹176 Cr
Budget left
Spent
₹29 Cr
Remaining
₹176 Cr
Total
₹205 Cr
Project Approved
Construction / Implementation
Original End Date
26/07/2028
Revised Completion
Completed
Project is within original budget of ₹338 Cr — no cost escalation recorded.
Expenditure stands at ₹29 Cr, which is 14.3% of the revised project cost.
Remaining budget: ₹176 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.