CONSTRUCTION OF 300 BEDDED HOSPITAL AT HARIDWAR
Original Cost
₹102 Cr
Baseline estimate
Revised Cost
₹298 Cr
Latest approved cost
Expenditure
₹340 Cr
Spent to date
Utilization
114.3%
Of revised budget
Cost Status
+191.8%
+₹196 Cr increase
Remaining
₹0 Cr
Budget left
Budget Utilization
114.3%Spent
₹340 Cr
Remaining
₹0 Cr
Total
₹298 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹102 Cr
Revised Cost
₹298 Cr
Increase
+₹196 Cr
Escalation
+191.8%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/10/2024
Revised Completion
31/07/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹196 Cr (191.8%) from the original estimate of ₹102 Cr.
Expenditure stands at ₹340 Cr, which is 114.3% of the revised project cost.
Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Healthcare. Ministry: Ministry of Labour and Employment.
CONSTRUCTION OF 300 BEDDED HOSPITAL AT HARIDWAR is a centrally-funded infrastructure project under Ministry of Labour and Employment, in the Healthcare sector. The original approved cost is ₹102.00 Cr, later revised to ₹297.63 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "CONSTRUCTION OF 300 BEDDED HOSPITAL AT HARIDWAR"?
- CONSTRUCTION OF 300 BEDDED HOSPITAL AT HARIDWAR is a centrally-funded infrastructure project under the Ministry of Labour and Employment, tracked through the Investment Project Monitoring (IPM) system. Sector: Healthcare. State: Uttarakhand. Original cost: ₹102 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹102 Cr and has been revised to ₹298 Cr — a cost overrun of +191.8%. Expenditure to date: ₹340 Cr (114.3% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- CONSTRUCTION OF 300 BEDDED HOSPITAL AT HARIDWAR is under the Ministry of Labour and Employment in the Healthcare sector. Project code: 612259. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. CONSTRUCTION OF 300 BEDDED HOSPITAL AT HARIDWAR is one of several Bihar projects tracked under the Healthcare sector on the IPM system.