Construction of 200 bed ESI Hospital at Bommasandra, Karnataka
Original Cost
₹278 Cr
Baseline estimate
Revised Cost
₹278 Cr
Latest approved cost
Expenditure
₹81 Cr
Spent to date
Utilization
29.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹197 Cr
Budget left
Budget Utilization
29.0%Spent
₹81 Cr
Remaining
₹197 Cr
Total
₹278 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
12/01/2027
Revised Completion
28/05/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹278 Cr — no cost escalation recorded.
Expenditure stands at ₹81 Cr, which is 29.0% of the revised project cost.
Remaining budget: ₹197 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Healthcare. Ministry: Ministry of Labour and Employment.
Construction of 200 bed ESI Hospital at Bommasandra, Karnataka is a centrally-funded infrastructure project under Ministry of Labour and Employment, in the Healthcare sector. The original approved cost is ₹278.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of 200 bed ESI Hospital at Bommasandra, Karnataka"?
- Construction of 200 bed ESI Hospital at Bommasandra, Karnataka is a centrally-funded infrastructure project under the Ministry of Labour and Employment, tracked through the Investment Project Monitoring (IPM) system. Sector: Healthcare. State: Karnataka. Original cost: ₹278 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹278 Cr has not been significantly revised. Expenditure: ₹81 Cr (29.0% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of 200 bed ESI Hospital at Bommasandra, Karnata is under the Ministry of Labour and Employment in the Healthcare sector. Project code: 612745. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 200 bed ESI Hospital at Bommasandra, Karnata is one of several Bihar projects tracked under the Healthcare sector on the IPM system.