Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /IPM Dashboard
  3. /Chhota Udaipur - Dhar New Line Project [157 km]
RailwaysIPM · Central Project#705454

Chhota Udaipur - Dhar New Line Project [157 km]

Ministry of RailwaysMadhya PradeshData: 2026-05
Revised Cost: ₹1794 CrUtilization: 101.8%

Original Cost

₹1794 Cr

Baseline estimate

On Budget

Revised Cost

₹1794 Cr

Latest approved cost

Expenditure

₹1827 Cr

Spent to date

Utilization

101.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹0 Cr

Budget left

Budget Utilization

101.8%
0%25%50%75%100%

Spent

₹1827 Cr

Remaining

₹0 Cr

Total

₹1794 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/12/2025

Revised Completion

27/12/2025

Completed

Project Details

Project Code705454
SectorRailways
MinistryMinistry of Railways
StateMadhya Pradesh
Data Month2026-05

Financial & Timeline

Original Cost₹1794 Cr
Revised Cost₹1794 Cr
Expenditure₹1827 Cr
Original End Date27/12/2025
Revised Date27/12/2025

Project Intelligence

Project is within original budget of ₹1794 Cr — no cost escalation recorded.

Expenditure stands at ₹1827 Cr, which is 101.8% of the revised project cost.

Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Frequently Asked Questions

What is IPM project "Chhota Udaipur - Dhar New Line Project [157 km]"?
Chhota Udaipur - Dhar New Line Project [157 km] is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Madhya Pradesh. Original cost: ₹1794 Cr.
What is the cost overrun for this Bihar IPM project?
The original cost of ₹1794 Cr has not been significantly revised. Expenditure: ₹1827 Cr (101.8% of cost). Data as of 2026-05.
Which ministry is responsible for this project?
Chhota Udaipur - Dhar New Line Project [157 km] is under the Ministry of Railways in the Railways sector. Project code: 705454. Bihar is one of the states tracked under the central IPM dashboard for this project.
What is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Chhota Udaipur - Dhar New Line Project [157 km] is one of several Bihar projects tracked under the Railways sector on the IPM system.

Related Resources

IPM

IPM Central Project Dashboard

All central infrastructure projects in Bihar

Projects

Bihar State Projects

State-funded infrastructure project tracker

NHAI

NHAI Drone Tracker

Real-time NHAI highway construction monitoring

Railway

Bihar Railway Projects

Railway infrastructure project tracker

RCD

Bihar RCD PMIS

State road and bridge project tracker

Tenders

Bihar Government Tenders

Procurement notices for infrastructure projects

Cabinet

Bihar Cabinet Decisions

Policy approvals for infrastructure

EC

EC & Forest Clearances

Environmental clearances for Bihar projects