Original Cost
₹407 Cr
Baseline estimate
Revised Cost
₹407 Cr
Latest approved cost
Expenditure
₹393 Cr
Spent to date
Utilization
96.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹14 Cr
Budget left
Spent
₹393 Cr
Remaining
₹14 Cr
Total
₹407 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
31/08/2026
Completed
Project is within original budget of ₹407 Cr — no cost escalation recorded.
Expenditure stands at ₹393 Cr, which is 96.5% of the revised project cost.
Remaining budget: ₹14 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.