Original Cost
₹2269 Cr
Baseline estimate
Revised Cost
₹2269 Cr
Latest approved cost
Expenditure
₹7 Cr
Spent to date
Utilization
0.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹2262 Cr
Budget left
Spent
₹7 Cr
Remaining
₹2262 Cr
Total
₹2269 Cr
Project Approved
Construction / Implementation
Original End Date
31/12/2029
Revised Completion
Completed
Project is within original budget of ₹2269 Cr — no cost escalation recorded.
Expenditure stands at ₹7 Cr, which is 0.3% of the revised project cost.
Remaining budget: ₹2262 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.