Original Cost
₹178 Cr
Baseline estimate
Revised Cost
₹153 Cr
Latest approved cost
Expenditure
₹142 Cr
Spent to date
Utilization
92.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹11 Cr
Budget left
Spent
₹142 Cr
Remaining
₹11 Cr
Total
₹153 Cr
Project Approved
Construction / Implementation
Original End Date
18/07/2023
Revised Completion
08/04/2024
Completed
Project is within original budget of ₹178 Cr — no cost escalation recorded.
Expenditure stands at ₹142 Cr, which is 92.9% of the revised project cost.
Remaining budget: ₹11 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.