Original Cost
₹502 Cr
Baseline estimate
Revised Cost
₹784 Cr
Latest approved cost
Expenditure
₹432 Cr
Spent to date
Utilization
55.1%
Of revised budget
Cost Status
+56.2%
+₹282 Cr increase
Remaining
₹352 Cr
Budget left
Spent
₹432 Cr
Remaining
₹352 Cr
Total
₹784 Cr
Original Cost
₹502 Cr
Revised Cost
₹784 Cr
Increase
+₹282 Cr
Escalation
+56.2%
Project Approved
Construction / Implementation
Original End Date
31/12/2056
Revised Completion
01/04/2027
Completed
Cost has increased by ₹282 Cr (56.2%) from the original estimate of ₹502 Cr.
Expenditure stands at ₹432 Cr, which is 55.1% of the revised project cost.
Remaining budget: ₹352 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Power.