CoalIPM · Central Project +56.2% overrun#603293

Badam Coal Mining project of NTPC

Ministry of PowerJharkhand
Revised Cost: ₹784 CrUtilization: 56.4%Overrun: +₹282 Cr

Original Cost

₹502 Cr

Baseline estimate

+56% overrun

Revised Cost

₹784 Cr

Latest approved cost

Expenditure

₹442 Cr

Spent to date

Utilization

56.4%

Of revised budget

Escalated

Cost Status

+56.2%

+₹282 Cr increase

Remaining

₹342 Cr

Budget left

Budget Utilization

56.4%
0%25%50%75%100%

Spent

₹442 Cr

Remaining

₹342 Cr

Total

₹784 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹502 Cr

Revised Cost

₹784 Cr

Increase

+₹282 Cr

Escalation

+56.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2056

Revised Completion

01/04/2027

Completed

Project Details

Project Code603293
SectorCoal
MinistryMinistry of Power
StateJharkhand
Data Month2026-08

Financial Summary

Original Cost₹502 Cr
Revised Cost₹784 Cr
Expenditure₹442 Cr
Original End Date31/12/2056
Revised Date01/04/2027

Project Intelligence

Cost has increased by ₹282 Cr (56.2%) from the original estimate of ₹502 Cr.

Expenditure stands at ₹442 Cr, which is 56.4% of the revised project cost.

Remaining budget: ₹342 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Coal. Ministry: Ministry of Power.

Badam Coal Mining project of NTPC is a centrally-funded infrastructure project under Ministry of Power, in the Coal sector. The original approved cost is ₹502.00 Cr, later revised to ₹784.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Badam Coal Mining project of NTPC"?
Badam Coal Mining project of NTPC is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Coal. State: Jharkhand. Original cost: ₹502 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹502 Cr and has been revised to ₹784 Cr — a cost overrun of +56.2%. Expenditure to date: ₹442 Cr (56.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Badam Coal Mining project of NTPC is under the Ministry of Power in the Coal sector. Project code: 603293. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Badam Coal Mining project of NTPC is one of several Bihar projects tracked under the Coal sector on the IPM system.