BG Line
Original Cost
₹1605 Cr
Baseline estimate
Revised Cost
₹2514 Cr
Latest approved cost
Expenditure
₹1712 Cr
Spent to date
Utilization
68.1%
Of revised cost
Cost Overrun
+56.6%
+₹909 Cr
Remaining
₹802 Cr
Budget left
Spent
₹1712 Cr
Remaining
₹802 Cr
Total
₹2514 Cr
68.1%
Utilized
Original Cost
₹1605 Cr
Revised Cost
₹2514 Cr
Increase
+₹909 Cr
Escalation
+56.6%
Project Approved
Construction / Implementation
Original End Date
2024-03-31
Revised Completion
2027-01-31
Completed
Cost has increased by ₹909 Cr (56.6%) from the original estimate of ₹1605 Cr.
Expenditure stands at ₹1712 Cr, which is 68.1% of the revised project cost.
Remaining budget: ₹802 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.