Original Cost
₹667 Cr
Baseline estimate
Revised Cost
₹667 Cr
Latest approved cost
Expenditure
₹324 Cr
Spent to date
Utilization
48.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹343 Cr
Budget left
Spent
₹324 Cr
Remaining
₹343 Cr
Total
₹667 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2023
Revised Completion
31/12/2027
Completed
Project is within original budget of ₹667 Cr — no cost escalation recorded.
Expenditure stands at ₹324 Cr, which is 48.6% of the revised project cost.
Remaining budget: ₹343 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.