Original Cost
₹758 Cr
Baseline estimate
Revised Cost
₹779 Cr
Latest approved cost
Expenditure
₹470 Cr
Spent to date
Utilization
60.3%
Of revised budget
Cost Status
+2.8%
+₹21 Cr increase
Remaining
₹310 Cr
Budget left
Spent
₹470 Cr
Remaining
₹310 Cr
Total
₹779 Cr
Original Cost
₹758 Cr
Revised Cost
₹779 Cr
Increase
+₹21 Cr
Escalation
+2.8%
Project Approved
Construction / Implementation
Original End Date
31/01/2025
Revised Completion
31/03/2027
Completed
Cost has increased by ₹21 Cr (2.8%) from the original estimate of ₹758 Cr.
Expenditure stands at ₹470 Cr, which is 60.3% of the revised project cost.
Remaining budget: ₹310 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.