Original Cost
₹638 Cr
Baseline estimate
Revised Cost
₹1215 Cr
Latest approved cost
Expenditure
₹1049 Cr
Spent to date
Utilization
86.4%
Of revised budget
Cost Status
+90.4%
+₹577 Cr increase
Remaining
₹165 Cr
Budget left
Spent
₹1049 Cr
Remaining
₹165 Cr
Total
₹1215 Cr
Original Cost
₹638 Cr
Revised Cost
₹1215 Cr
Increase
+₹577 Cr
Escalation
+90.4%
Project Approved
Construction / Implementation
Original End Date
31/12/2025
Revised Completion
31/10/2026
Completed
Cost has increased by ₹577 Cr (90.4%) from the original estimate of ₹638 Cr.
Expenditure stands at ₹1049 Cr, which is 86.4% of the revised project cost.
Remaining budget: ₹165 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.