Original Cost
₹177 Cr
Baseline estimate
Revised Cost
₹177 Cr
Latest approved cost
Expenditure
₹3 Cr
Spent to date
Utilization
1.9%
Of revised budget
Cost Status
+0.2%
+₹0 Cr increase
Remaining
₹174 Cr
Budget left
Spent
₹3 Cr
Remaining
₹174 Cr
Total
₹177 Cr
Original Cost
₹177 Cr
Revised Cost
₹177 Cr
Increase
+₹0 Cr
Escalation
+0.2%
Project Approved
Construction / Implementation
Original End Date
28/02/2027
Revised Completion
28/02/2027
Completed
Cost has increased by ₹0 Cr (0.2%) from the original estimate of ₹177 Cr.
Expenditure stands at ₹3 Cr, which is 1.9% of the revised project cost.
Remaining budget: ₹174 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.