Original Cost
₹1883 Cr
Baseline estimate
Revised Cost
₹1896 Cr
Latest approved cost
Expenditure
₹919 Cr
Spent to date
Utilization
48.5%
Of revised budget
Cost Status
+0.7%
+₹13 Cr increase
Remaining
₹977 Cr
Budget left
Spent
₹919 Cr
Remaining
₹977 Cr
Total
₹1896 Cr
Original Cost
₹1883 Cr
Revised Cost
₹1896 Cr
Increase
+₹13 Cr
Escalation
+0.7%
Project Approved
Construction / Implementation
Original End Date
31/03/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹13 Cr (0.7%) from the original estimate of ₹1883 Cr.
Expenditure stands at ₹919 Cr, which is 48.5% of the revised project cost.
Remaining budget: ₹977 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.