Original Cost
₹1167 Cr
Baseline estimate
Revised Cost
₹1433 Cr
Latest approved cost
Expenditure
₹980 Cr
Spent to date
Utilization
68.4%
Of revised budget
Cost Status
+22.8%
+₹266 Cr increase
Remaining
₹453 Cr
Budget left
Spent
₹980 Cr
Remaining
₹453 Cr
Total
₹1433 Cr
Original Cost
₹1167 Cr
Revised Cost
₹1433 Cr
Increase
+₹266 Cr
Escalation
+22.8%
Project Approved
Construction / Implementation
Original End Date
28/10/2023
Revised Completion
31/10/2026
Completed
Cost has increased by ₹266 Cr (22.8%) from the original estimate of ₹1167 Cr.
Expenditure stands at ₹980 Cr, which is 68.4% of the revised project cost.
Remaining budget: ₹453 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.