Original Cost
₹1770 Cr
Baseline estimate
Revised Cost
₹2025 Cr
Latest approved cost
Expenditure
₹574 Cr
Spent to date
Utilization
28.4%
Of revised cost
Cost Overrun
+14.4%
+₹255 Cr
Remaining
₹1451 Cr
Budget left
Spent
₹574 Cr
Remaining
₹1451 Cr
Total
₹2025 Cr
28.4%
Utilized
Original Cost
₹1770 Cr
Revised Cost
₹2025 Cr
Increase
+₹255 Cr
Escalation
+14.4%
Project Approved
Construction / Implementation
Original End Date
2024-04-12
Revised Completion
2026-06-30
Completed
Cost has increased by ₹255 Cr (14.4%) from the original estimate of ₹1770 Cr.
Expenditure stands at ₹574 Cr, which is 28.4% of the revised project cost.
Remaining budget: ₹1451 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.