Original Cost
₹1772 Cr
Baseline estimate
Revised Cost
₹1772 Cr
Latest approved cost
Expenditure
₹500 Cr
Spent to date
Utilization
28.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1272 Cr
Budget left
Spent
₹500 Cr
Remaining
₹1272 Cr
Total
₹1772 Cr
Project Approved
Construction / Implementation
Original End Date
03/12/2022
Revised Completion
31/07/2026
Completed
Project is within original budget of ₹1772 Cr — no cost escalation recorded.
Expenditure stands at ₹500 Cr, which is 28.2% of the revised project cost.
Remaining budget: ₹1272 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.