to Km 49.000 Package-I of NH327E
Original Cost
₹1283 Cr
Baseline estimate
Revised Cost
₹1283 Cr
Latest approved cost
Expenditure
₹599 Cr
Spent to date
Utilization
46.7%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹684 Cr
Budget left
Spent
₹599 Cr
Remaining
₹684 Cr
Total
₹1283 Cr
46.7%
Utilized
Project Approved
Construction / Implementation
Original End Date
2024-01-09
Revised Completion
Completed
Project is within original budget of ₹1283 Cr — no cost escalation recorded.
Expenditure stands at ₹599 Cr, which is 46.7% of the revised project cost.
Remaining budget: ₹684 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.