Original Cost
₹1410 Cr
Baseline estimate
Revised Cost
₹1674 Cr
Latest approved cost
Expenditure
₹609 Cr
Spent to date
Utilization
36.4%
Of revised budget
Cost Status
+18.7%
+₹264 Cr increase
Remaining
₹1065 Cr
Budget left
Spent
₹609 Cr
Remaining
₹1065 Cr
Total
₹1674 Cr
Original Cost
₹1410 Cr
Revised Cost
₹1674 Cr
Increase
+₹264 Cr
Escalation
+18.7%
Project Approved
Construction / Implementation
Original End Date
14/04/2026
Revised Completion
31/07/2027
Completed
Cost has increased by ₹264 Cr (18.7%) from the original estimate of ₹1410 Cr.
Expenditure stands at ₹609 Cr, which is 36.4% of the revised project cost.
Remaining budget: ₹1065 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.