Original Cost
₹2083 Cr
Baseline estimate
Revised Cost
₹2545 Cr
Latest approved cost
Expenditure
₹866 Cr
Spent to date
Utilization
34.0%
Of revised budget
Cost Status
+22.2%
+₹462 Cr increase
Remaining
₹1679 Cr
Budget left
Spent
₹866 Cr
Remaining
₹1679 Cr
Total
₹2545 Cr
Original Cost
₹2083 Cr
Revised Cost
₹2545 Cr
Increase
+₹462 Cr
Escalation
+22.2%
Project Approved
Construction / Implementation
Original End Date
19/10/2023
Revised Completion
31/03/2027
Completed
Cost has increased by ₹462 Cr (22.2%) from the original estimate of ₹2083 Cr.
Expenditure stands at ₹866 Cr, which is 34.0% of the revised project cost.
Remaining budget: ₹1679 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.